Section 53: Prohibition on concluding contract during reconsideration or review proceedings

(1) If a procurement process is subject to—

(a) a reconsideration in accordance with section 35, a procuring institution may not conclude a contract with the successful bidder within 10 days after completion of the reconsideration; or

(b) review in accordance with section 47, a procuring institution may not conclude a contract with the successful bidder prior to completion of the review process.

(2) If an emergency requires procurement for a matter that is the subject of a reconsideration or a review as envisaged in subsection (1), emergency procurement may take place as envisaged in section 63(1)(a)(xi).